The Project
New Project desciption :
-
Cable cars with 8 seats each
-
Departure station :
-
Elegant wooden structure
-
Recovery of foundations and existing concrete slab
-
Includes access by elevator
-
-
980 people per hour, extensible to 1'200 pers./h (vs 600 pers./h current)
-
Arrival station :
-
Maintenance of existing building
-
Ideal calendar
September 2017
-
Project details given to OFT ( office fédéral des transports) in Bern for their examination.
Autumn 2017
-
Registration of the Isenau project by the Grand Conseil.
-
Investigation
Winter 2017 / 2018
-
Vote by the Grand Conseil
-
Authorisation of construction
-
Order the new Télécabine
Spring 2018
-
Demolition of the old and construction of the new télécabine
December 2018
-
Inauguration of the new télécabine